Summary
Instead of patching North Boulevard after gas main work, Nicor Gas will pay the Village up to $70,000 so the street can be fully resurfaced as part of the Oak Park Avenue Streetscape project.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Sep 24, 2026.
Impact analysis
Brings up to $70,000 from Nicor Gas toward resurfacing, with the Village's share estimated around $72,000 at contract prices.
Drivers and residents along North Boulevard, who get a full resurfacing instead of a patch.
None identified.
Mentions & discussions (2)
President and Board of Trustees — November 4, 2026
Instead of patching North Boulevard after gas main work, Nicor Gas will pay the Village up to $70,000 so the street can be fully resurfaced as part of the Oak Park Avenue Streetscape project.
Finance Committee — September 24, 2026
Staff reviewed $1.3 million in motor fuel tax capital expenditures, highlighting upcoming federally funded resurfacing on Austin Boulevard and Ridgeland Avenue. Trustees pressed staff on pedestrian safety, intersection crash concerns at Garfield and Austin, and the future of temporary neighborhood greenway diverters.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Oak Park
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.